Request for Proposals for Scope III Bid Solicitation 11 SFPUC - Southeast Plant New Headworks Construction

Bid due

10/29/2021
2:00 PM

  • Type Professional Services
  • Department Infrastructure
BACK TO CONTRACTS & BIDS LIST
Project Description
While information may be periodically added to this Project Description page, it exists only as a courtesy. Please only rely on official updates provided by Sundt-Walsh and on Sundt-Walsh's SmartBid website: https://secure.smartbidnet.com/LAPW

PROJECT DESCRIPTION:
The intent of this project is to replace the existing Headworks Facility at the SE Water Pollution Control Plant with a new all-weather 250 MGD Headworks Facility.  This is solicitation 11 for Scope III New Headworks Construction.     

SCOPE / DRAWINGS:

The drawings for Scope III are included in the Plan Room on Smartbidnet.com.  The scopes being sought for this project are as follows:
3-21     Metal Wall Fabric Cladding and Formed Metal Panels - 20% LBE Requirement
3-24     Roofing - 20% LBE Requirement
3-25     Dampproofing, Concrete Sealing, Joint Sealant, and Caulking - 20% LBE Requirement
3-40     Overhead Crane - Procurement Only - 0% LBE
3-49     Fence and Gates - 20% LBE Requirement
3-53     Bird Control Devices - 0% LBE Requirement
3-75     Self-Contained Compactor - Procurement Only - 0% LBE Requirement
3-79     Masonry - 20% LBE Requirement
                                                          
PRE-QUALIFICATION OF PROSPECTIVE SUBCONTRACTORS:  The Owner has determined that subcontractors who submit bids to Sundt/Walsh on this Project must be pre-qualified.  Those subcontractors who pre-qualify will be allowed to bid on the above Scope of Work. 
 
Interested firms may obtain Pre-qualification Documents on the Smartbidnet.com website or by contacting David Cooley, via e-mail at dcooley@sundt.com

LOCAL BUSINESS ENTERPRISE (LBE) REQUIREMENTS: 
The following project-wide LBE participation requirement is: LBE-15%. Each Bid Package has a specific LBE requirement as indicated above.  Any proposals that fail to meet the Bid Package LBE requirement will be deemed non-responsive.

 


DISADVANTAGED BUSINESS ENTERPRISE (DBE) REQUIREMENTS: All subcontractors are hereby notified that it is expected that work to be performed under this contract will be in full or in part financed by the Clean Water State Revolving Fund (SRF), administered by the United States Environmental Protection Agency (US EPA) and the State Water Resources Control Board (SWRCB). Bidders shall comply with all applicable terms and conditions, special provisions, and reporting requirements, as set forth in these specifications, and as may be required by federal law, rule, or regulation.  Additionally, meeting the project-wide Fair Share Objective is encouraged: MBE-6.4%, WBE-2.0%. Refer to Contract Section 00 48 10.01, Paragraph 2 for more information.

 
BID DUE DATE:  All bid documents must be submitted no later than October 29, 2021 by 2:00 p.m, California Time.

Confidentiality of the information provided will be respected to the extent permitted by law.

QUESTIONS:  Direct all project specific questions to David Cooley at Sundt/Walsh. All questions should be submitted via e-mail. The e-mail address is Dcooley@sundt.com.

 

 

Request for proposal

  • ESTIMATED COST
    N/A
  • DUE DATE
    10/29/2021
  • DUE TIME
    2:00 PM
  • DURATION
  • LOCATION
  • CONTACT
    David Cooley, Dcooley@sundt.com

Pre-Submittal Conference

  • DATE
  • TIME
  • ATTENDANCE
    Not Mandatory
  • LOCATION
  • ADVERTISEMENT DATE
LIST OF CERTIFIED LBE FIRMS AT HRC WEBSITE