Bid Details
WW-742
Southeast Water Pollution Control Plant 040/041/043 Health & Safety Improvements [BID TABULATION]

Bid due

04/18/2024
2:00 PM

  • Type Construction
  • Department Infrastructure Division
BACK TO CONTRACTS & BIDS LIST
Project Description
An electronic version of the bidding forms, contract specifications, drawings, and available project information are available by request. To request these materials, email qbd@sfwater.org with this Contract No. WW-742, the firm name, full address, email address, phone number, copy of contractor’s license or business card, and a copy of a government-issued identification. Visit https://webapps.sfpuc.org/bids/ for updates.   Please be advised that prior to receiving these materials, all requestors will be required to complete, sign, and comply with a Confidentiality Agreement.

The objective of the project is to provide health and safety improvements, as well as electrical reliability, to SEP Primary Sedimentation Buildings.  The work is to be performed in San Francisco, California. The Engineer's estimate is $20,000,000. 

Bid discounts may be applied as per San Francisco Administrative Code Chapter 14B and Section 2.01 of CMD Attachment 1. The Local Business Enterprise (LBE) subcontracting requirement is 15.00%. The LBE subcontracting requirement can only be met with CMD certified San Francisco Micro and Small-LBEs.  The LBE subcontractor participation requirement for this Contract is below 20% due to the following: This project has a high level of complexity when it comes to the scope of work, primarily the electrical work. The contractor will be installing provisions to run SEP 040/041 during a power shut down to allow both maintenance and connections to an existing substation. This critical load system is comprised of a manual transfer switch, portable generator connection and a portable generator. The contractor will be required to install the critical load test the critical load equipment in a short window that is critical to WWE operation of the facility. During construction, the contractor will be required to coordinate and switch between permanent and temporary power, potentially more than once. Failure to properly transfer between temporary and permanent power can have severe operational consequences. This project also has many weather constraints. Since Southeast Plant (SEP) will be in operation during construction, work will have to be tailored to the dry and wet weather seasons and ensure the building is operational when required by WWE. Lastly, SEP has multiple projects occurring at the same time. This adds an even higher level of complexity since the contractor will have to coordinate with several different projects. SFPUC-LBEs cannot be counted towards meeting the LBE subcontracting requirement(s).  Prime and Joint Venture level LBE participation cannot be counted towards meeting any of the LBE subcontracting requirement(s). LBE subcontractors must be certified with CMD in the scope of work they are being listed to perform. All Bidders shall submit documented Good Faith efforts with their Bids as directed on CMD Form 2B, except those who exceed the above-stated subcontracting requirement(s) by at least 35%. Refer to CMD Attachment 1. Failure to comply with Chapter 14B requirements may result in a Bid being deemed non-responsive and ineligible for Contract award.  Please contact Adriana Duran at (415) 598-7368 or Adriana.duran@sfgov.org for further information.  Subcontracting opportunities may include, but not limited, to the following major types of work: Class A General Engineering Contractor; C-10 Electrical; C-33 Painting and Decorating; D-6 – Concrete. Please refer to Section 01 60 00 in the Specifications regarding the purchase of equipment to achieve the LBE subcontracting participation requirement.

Interested Bidders are encouraged to attend by remote means a teleconference pre-bid and contractor networking conference to be held on 3/15/2024 at 10:00 A.M. To participate by remote means, please access the meeting at this website: https://sfwater.zoom.us.  The Meeting ID is 895 2181 1523 and meeting Passcode is 322881. To join, enter Meeting ID and click Join.  When prompted, enter the meeting Passcode.  To participate by phone, dial +1.213.338.8477 and enter the Meeting ID followed by # key.  When prompted, enter the meeting Passcode and # key.  Attendance of remote attendees will be completed at the end of the pre-bid meeting. 

A site inspection will be held at Southeast Plant,
750 Phelps Street, at 10:00 A.M. on 3/19/2024.

SFPUC encourages Bidders to complete the Safety Prequalification Web Form at https://sfpuc.org/construction-contracts/contract-opportunities-payments/prequalify-construction at least 3-weeks prior to the date of Bid opening in accordance with Section 00 21 13 – Instructions to Bidders.  Bidders are required to pass the Safety Prequalification prior to SFPUC considering their bid submission complete.  SFPUC will notify Bidders that have passed the Safety Prequalification prior to or on the date of Bid opening.  Refer to Section 00 21 13 – Instructions to Bidders, “Bidder Qualifications” and the website listed above for additional information.

A Class “A California Contractors License is required to bid.  Furthermore, each listed subcontractor must possess appropriate active licenses for the work each subcontractor will be performing.

Request for proposal

  • ESTIMATED COST
    $20,000,000
  • DUE DATE
    04/18/2024
  • DUE TIME
    2:00 PM
  • DURATION
  • LOCATION
    https://sfwater.zoom.us/j/87811945391?pwd=Q0JOVzRCbnBCb0lFWlRJbUt2MWRudz09
  • CONTACT
    Contract Administration Bureau at QBD@sfwater.org

Pre-Bid Conference

  • DATE
    03/15/2024
  • TIME
    10:00 AM
  • ATTENDANCE
    Not Mandatory
  • LOCATION
    https://sfwater.zoom.us/j/89521811523?pwd=dGdHem5LR1RsU0ZiU3NUYjAxT0FUUT09
  • ADVERTISEMENT DATE
    03/05/2024
LIST OF CERTIFIED LBE FIRMS AT HRC WEBSITE